1.0?????? Introduction & Background of the Case
The purpose of this descriptive case study is not to elaborate on the complicated details of EVM, but to elaborate on the fundamentals of activity based costing (ABC) in the context of project management. The opportunity is to develop an integrated management system utilizing ABC concepts to plan, measure, and control costs that allow managers to focus on process performance and to make informed decisions along the product/service/project life cycle.
It is assumed that the reader is familiar with common project management terms. However, Figure 01: Wideman Comparative Glossary in the appendix contains a web link to Wideman Comparative Glossary of Common Project Management Terms v3.1 for those readers unfamiliar with project management terminology.
Click web link: http://www.maxwideman.com/pmglossary/index.htm
Figure 01: Wideman Comparative Glossary
(Wideman, 2002)
1.1?????? Discussion & Analysis of Critical Issues
Organizations are faced with many challenges during this time of economic recession. The most common organizational reactions are to button down the hatches, secure the turf, and start chopping staff positions. Dysfunctional organizations tend to always look in the rearview mirror and employ managers that make snap decisions without sufficient data, which often result in organizational demise. Forward looking organizations that seek out opportunities during a time of economic recession tend to focus on process improvement initiatives such as, business-process analysis; activity based costing, life cycle compression metrics, among other things.
This case study assumes the forward looking perspective. The next section introduces activity based costing, which is followed by a brief discussion of concepts and methods found during the research of several other independent case studies. Then an introduction and description of some basic project management processes. Finally, continued by a simplicity case and finally the conclusion.
2.1?????? Activity Based Costing (ABC) – Introduction
ABC was developed as a continuous improvement initiative of the accounting information system. Original, ABC was used as a product costing methodology, but is now being used as a cost management tool in many different functions of business (Awasthi, 1994, p 8). A couple of differences between ABC and traditional cost systems are 1) costs are traced to cost objects by identifying cost drivers and 2) costs are traced on the basis of the structural or hierarchical level at which costs are incurred. Therefore, ABC provides more accurate cost estimates of the product or service and the corresponding activities than traditional costing (Kee, 1995, p 49).
2.2?????? Activity Based Costing (ABC) – Discussion
It is important to note that in traditional costing the assumption is that products consume resources. ABC contrasts traditional costing by assuming that products consume activities and activities consume resources. Once the product or service activities are identified, costs are allocated to the product or service according to the amount incurred by those activities. This method of allocating costs provides a benefit for making decisions regarding different types of profitability and project accounting (Awasthi, 1994, pp 9-10).
There are two sets of costs related to the accuracy of ABC cost information, 1) cost of measurement and 2) cost of decision error. As the accuracy of measurement goes down the cost of decision error goes up. Detail is an important factor in the success of a ABC system, but the detail must be value add. It is important to control changes brought on by environmental factors (competition, volatility, profit margins, etc…) while still allowing for diversity throughout the life cycle of the product or service (Awasthi, 1994, p 11). So how can one ensure accuracy in measurements for better decision making? The key is to identify and analyze the most optimal cost drivers that trace the costs of the activities back to the product or service.
2.3?????? Activity Based Costing (ABC) – Activity Identification & Analysis
Cost drivers are linked to business process mapping and activity analysis in order to obtain rigid data for measurement analysis. Figure 02 depicts a two stage process that traces expenses through activities to cost objects.
Figure 02: Basic ABC Flow
The first stage traces expenses from the department or organizational level budget to activities that are assigned to resources (labor, space, materials, and suppliers). For example, a labor resource is allocated to an activity at 100% over a duration of time equating to a unit of work converted to an activity cost. In the second stage, activity costs are traced through the activity cost drivers to the cost objects, i.e. products and/or services. This stage is concerned with explaining the causes of work and what things cost. Managers that focus on process drivers and cost drivers have a more detailed understanding of activity costs and associated activity dependencies. Therefore, managers can make better decisions on areas in need for process improvement instead of shooting from the hip (Brandt, Levine & Gourdoux, 1999, pp 22-25).
ABC provides a hierarchical structure of detail. The challenge for managers is to ensure an optimal amount of detail that achieves balance and accuracy. Next we discuss cost driver optimization.
2.4?????? Activity Based Costing (ABC) – Cost Driver Optimization
Managers chose cost drivers for planning and control purposes. Choosing too many cost drivers? and the system is bogged down creating extra costs and inefficiency problems. Managers must strive to strike a balance between accuracy benefits and costs of data management. Babad & Balachandran indicate in their article, “Cost Driver Optimization in Activity-Based Costing”, that an optimal number of cost drivers generally discriminates and captures most of the incurred costs, and identify a priority order that specifies which low-priority and relatively insignificant activities will be combined to save costs without sacrificing much accuracy (Babad & Balachandran, 1993, p 565).
At this point the concepts of ABC have been introduced and discussed as a process object for organizations to utilize. The next section expands on the project management context as it relates to ABC.
3.0?????? Project Management and ABC – Introduction & Background
The project manager is responsible for the scope, schedule, and budget (triple constraints) at the project level. A project is characterized as a progressively elaborated temporary endeavor undertaken to create a unique product, service, or result (PMBOK, 2004, p 5). Projects generally exist as a sub-set of the organization.
3.1?????? Project Management and ABC – Project Life Cycle
Project managers or organizations parcel projects into phases for better management control. Phases are typical identified within a life cycle. The phases of the project life cycle are depicted in Figure 03: Project Life cycle. The project life cycle is not intended to represent the project management process. The project life cycle typically defines 1) what technical work to do in each phase; 2) when the deliverables are to be generated in each phase; 3) who is involved in each phase; 4) how to control and approve each phase (PMBOK, 2004, p 20).
Figure 03: Project Life cycle
(PMBOK, 2004, p 68)
3.2?????? Project Management and ABC – Work Breakdown Structure (WBS)
In this process, project deliverables and objectives are subdivided into smaller more manageable components. A WBS is a deliverable-oriented hierarchical decomposition of the work. This is the activity analysis concept mentioned previously in section 2.3 Activity Based Costing (ABC) – Activity Identification & Analysis. Work is planned to the lowest-level WBS component called a work package. Work packages can be scheduled, monitored, and controlled.
Figure 04: WBS Example 01 in a generic representation of a WBS. Notice the phases and deliverables located throughout the WBS. Also notice the work packages at lowest-levels of the WBS. Figure 05: WBS Example 02 is a software development representation of a WBS. The activity costs are traced to the first level and are also the phases of the project. The deliverables are at level two, where as the resource and activity drivers are at the lowest-level. As mentioned before, the lowest level is a work packages and can be scheduled, monitored, and controlled.
Figure 04: WBS Example 01
(PMBOK, 2004, p 114)
Figure 05: WBS Example 02
(PMBOK, 2004, p 116)
3.3?????? Project Management and ABC – Responsibility Assignment Matrix (RAM)
To define the cost objects a PM will use a RAM. Max Wideman defines the RAM as an important tool that correlates the work required by a Contract Work Breakdown Structure (CWBS) element to the functional organization responsible for accomplishing the assigned tasks. The responsibility assignment matrix is created by intersecting the CWBS with the program Organizational Breakdown Structure (OBS). This intersection identifies the cost account (Wideman, 2002). Figure 06: RAM Example 01 and Figure 07: RAM Example 02 are great examples of how cost objects are realized as cost accounts. All the activity estimates, risks, and incurred costs related to the cost account are summarized at these management control points. This gives the PM tremendous insight to the health of his/her project.
Figure 06: RAM Example 01
(Valuation Opinions, Inc., 2008)
Figure 07: RAM Example 02
(Performance Management Associates, Inc., 2008)
3.4?????? Project Management and ABC – Resource Loaded Network (RLN)
A RLN is an integration of schedule and cost and is represented as a network of time phased resource loaded activities sequentially ordered across the phases of the project life cycle. A resource loaded activity is also called a work package. The longest path through the sequential network of activities is known as the critical path. The PM uses what is known as the critical path method to focus on those activities along this path to ensure the project delivers on time and within budget. A PM can exercise a critical path analyses, what-if drills, and PERT analyses to monitor time and cost impacts.? Figure 08: Critical Path represents a network of activities with the critical path indicated in bold red.
Figure 08: Critical Path
(Construction-planning-and-control.com, 2008)
3.5?????? Project Management and ABC – Descriptive Case
Project staff utilize ABC concepts throughout the project life cycle and may not even know it. One of the first jobs for the project manager (PM) and team to conduct is a delineation of the deliverables and objectives defined in the statement of work (SOW) using ABC concepts. A simple example of this is when a project sponsor initiates the transfer of scope (deliverables and objectives) to be performed within a stated timeline and within a specific budget to the PM via the project charter. Before establishing the activity costs, the scope must be decomposed into a work breakdown structure (WBS). The PM aligns the WBS with the organizational breakdown structure (OBS) to determine control accounts and assign control account managers (CAM). CAMs develop the scope description in the WBS dictionary, which is comprised of inputs, outputs, assumptions, constraints, risks, deliverable milestones dates, among other things. The resources are assigned to activities and time phased within a resource loaded network (RLN) or more commonly known as the schedule. It is the basis of estimate (BOE) artifact that explains the rationale behind the costs related to the time-phasing of activities and substantiates the activity cost estimates. All of the appropriate technical, schedule, and cost artifacts are captured into one project management plan (PMP).The technical baseline, schedule baseline, and the cost baseline are integrated into a performance measurement baseline (PMB), which establishes the foundation for performance tracking and estimate to complete forecasting.
4.0?????? Conclusions & Recommendations
ABC is absolutely applicable in the context of project management. Organizational managers and project managers alike need a method to manage vast amounts of activities. Tracing cost to the product/service/project element gives managers an advantage to make informed decision for process improvement. ABC is one method of many and project management is the discipline of tactical processes to implement business strategy. Organizations that focus on opportunities and process improvement initiatives may just come out on top as winners in this most uncertain time of economic despair.

References
Awasthi, V. (1994, July). ABC’s of activity-based costing. Industrial Management, 36(4), 8.
Retrieved January 24, 2009, from EBSCO MegaFILE database.
Babad, Y., & Balachandran, B. (1993, July). Cost driver optimization in activity-based costing.
Accounting Review, 68(3), 563-575. Retrieved January 24, 2009, from EBSCO
MegaFILE database.
Brandt, M., Levine, S., & Gourdoux, J. (1999, January). Application of activity-based
cost management. Professional Safety, 44(1), 22. Retrieved January 24, 2009, from
EBSCO MegaFILE database.
Construction-planning-and-control.com. (2008) Critical path. Retrieved January, 24, 2009, from
http://www.construction-planning-and-control.com/images/CPMdemoCP.jpg
Kee, R. (1995, December). Integrating activity-based costing with the theory of constraints to
enhance production-related decision-making. Accounting Horizons, 9(4), 48-61.
Retrieved January 24, 2009, from EBSCO MegaFILE database.
Performance Management Associates, Inc. (2008). Responsibility assignment matrix. Retrieved
January 24, 2009, from http://www.pmassoc.com/images/matrix.gif
Project Management Institute (PMI). (2004). A guide to the project management body of
knowledge (PMBOK Guide) (3rd ed.). Philadelphia, Pennsylvania: PMI
Schiff, J., & Schiff, A. (2008, October). Focusing on cost management during economic
downturns. Financial Executive, 24(8), 49-50. Retrieved January 24, 2009, from EBSCO
MegaFILE database.
Valuation Opinions, Inc. (2008). Responsibility assignment matrix. Retrieved January 24, 2009,
from http://www.valuation-opinions.com/ev/ram/lasso
Wideman, R. Max. (2002, March). Wideman comparative glossary of common project
management terms v3.1. Retrieved January 24, 2009, from
http://www.maxwideman.com/pmglossary/index.htm